University of Applied Sciences Münster
Refurbishment and extension of Building Section E3 at the Steinfurt Campus of the Münster University of Applied Sciences
- Design:PLAN FORWARD GmbH
- GFA:3,045 m²
- Services:General planning, HOAI LPH 1 - 8
- Completion:2023
- Client:Bau- und Liegenschaftsbetrieb NRW - Münster branch
Project description
PLAN FORWARD GmbH was commissioned with the planning of the refurbishment and modernization of the facade, as well as the interiors of Building Section E3 of the Steinfurt Campus of the Münster University of Applied Sciences. W+P Gesellschaft für Projektrealisierung mbH, a sister company of PLAN FORWARD, took over the general planning.
In this constellation, the two teams have already successfully completed the renovation and modernization work of the facade, as well as the interiors of the building part A10 of the Steinfurt Campus in 2019.
The follow-up contract was also implemented on budget and on time, so that the new premises were move-in ready as planned in April 2023.