New construction of the "Hardenbergstraße "district sports facility in Mülheim an der Ruhr

After being commissioned in 2013 by the “ImmobilienService” of the City of Mülheim an der Ruhr, PLAN FORWARD GmbH, together with its sister company, W+P Gesellschaft für Projektrealisierung mbH, was responsible for the general planning as well as the architecture and object planning of the new Hardenbergstraße district sports facility.

The laying of the foundation stone on November 4, 2014 marked the starting point for the first structural engineering stage on the 2.4-hectare site after an intensive coordination phase of only three months with the client, the project manager and the users and operators of the facility.

Accompanying the execution planning by PLAN FORWARD, the site had already been prepared for the construction measures since February 2014. The site was cleared of existing vegetation and the existing height level of up to 3.5 meters was adjusted.

By the end of 2015, two large synthetic turf pitches, a grandstand between the pitches, a clubhouse with changing rooms and sanitary facilities as well as catering facilities and a parking lot with 96 parking spaces was built on the sports grounds.